Pricing guide

How to Bid Construction Jobs

A construction bid sets a price against a specific set of drawings, quantities and site conditions. Start by deciding what work you can deliver, measure it from the current documents, then estimate what your crew and suppliers need to complete it. A low unit price can still lose money if the scope requires extra mobilization, restricted work hours or subcontracted items you overlooked. The municipal bid tabs below show prices contractors submitted for defined work. The sidewalk example uses one bidder’s published units to demonstrate how a measured scope becomes a bid schedule.

Published prices and what they cover

Sources checked . Figures are in USD. A provider’s own rate applies to its stated service and area.

Service or line itemPublished amountScope and source
4-inch concrete sidewalk$9.63–$9.89 per square footTwo submitted contractor unit bids on the City of Dickinson’s 2026 Sidewalk Program. City of Dickinson 2026 sidewalk bid tabulation
Concrete removal$2.25–$2.27 per square footThe Dickinson project listed separate items for concrete removal, concrete pavement removal, and reinforced concrete removal. City of Dickinson 2026 sidewalk bid tabulation
Aggregate Base Course CL 5$88.00–$88.38 per cubic yardTwo bids for the specified base course on the same Dickinson project. City of Dickinson 2026 sidewalk bid tabulation
Mobilization$740–$875 eachThe Dickinson bid tab listed eight mobilization units. These are the two prices per unit. City of Dickinson 2026 sidewalk bid tabulation
6-inch sidewalk or driveway$12.48–$12.77 per square footTwo submitted rates for the Dickinson bid item with thicker pavement. City of Dickinson 2026 sidewalk bid tabulation
4-inch concrete sidewalk on a mill and overlay job$7.89–$18.00 per square footFour contractor unit bids for item 75 in Alternate Bid 2 on the City of Hastings’ 2026 project, which listed 80 square feet. City of Hastings 2026 mill and overlay bid tabulation

Example estimate

Bid schedule for removing and replacing 320 square feet of sidewalk

Worked example using published price inputs and assumed quantities.

DescriptionQtyUnit priceAmount
Remove existing sidewalk concreteCity of Dickinson 2026 sidewalk bid tabulation320 sq ft$2.25$720.00
Aggregate Base Course CL 5City of Dickinson 2026 sidewalk bid tabulation4 cu yd$88.38$353.52
Install 4-inch concrete sidewalkCity of Dickinson 2026 sidewalk bid tabulation320 sq ft$9.63$3,081.60
Mobilize crew and equipmentCity of Dickinson 2026 sidewalk bid tabulation1 item$875.00$875.00

Example subtotal before tax: $5,030.12

This arithmetic example assumes one 80-by-4-foot walk, 4 cubic yards of specified aggregate base and one mobilization. All unit prices come from Winn Construction’s submitted column in the City of Dickinson bid tab. The extensions are $720.00 for removal, $353.52 for aggregate, $3,081.60 for new sidewalk and $875.00 for mobilization, totaling $5,030.12 before any applicable tax or other work. The quantities are hypothetical. The published unit bids reflect the municipal project’s specifications and scale. Build your real price from your own project costs and check the payment descriptions before billing work under separate items.

Build this estimate

Read the invitation and decide whether to bid

Check the deadline, delivery instructions, start window and work schedule before you spend time on a takeoff. Review the scope against the equipment, crew and subcontractors you can actually secure. A site that keeps pedestrian access open during a concrete replacement can require extra barriers, smaller pours and more coordination than the same quantity at a closed site. If a specification or milestone is unclear, submit the question through the process described in the bid package.

List the documents your price covers. Identify drawing dates, specification sections, revisions and each addendum you receive. Compare the scope narrative with the drawings, plan notes and bid schedule. Write down any gap that changes quantities, finishes, protection or who supplies equipment. Check the next addendum before carrying an answer into the estimate. Keep the final document list with the bid so you can trace the assumptions behind the price during a scope review.

Walk the site when you can. Check truck turning room, laydown area, disposal access, public protection and existing work that must stay in service. Verify where the customer expects you to stage materials and what working hours they can accommodate. On a sidewalk job, access for a ready-mix truck can determine whether you need additional transport or handling. Record which constraints you observed and which details you still need the project contact to confirm.

Build a takeoff that follows the bid units

Start with work you can measure. Take off demolition and new work separately, and label the drawing or field measurement each quantity came from. A proposed 80-foot run of 4-foot-wide sidewalk measures 320 square feet. Calculate excavation, compacted base and concrete volume with their own dimensions and units. Compare the volume you expect to buy with the unit the owner will pay for, since an order quantity and a bid quantity can use different measurement rules.

Break measured work into operations the crew will perform. Concrete replacement can include saw cutting at the ends, breaking and loading slabs, preparing the base, setting forms, placing and finishing concrete, curing, and returning to remove forms or barriers. Estimate labor and equipment hours from your own production records or a subcontractor’s written scope. Allow for setup and cleanup each time the crew has to leave and remobilize, and account for shared equipment if another phase needs it.

Check the payment description attached to each unit price. A per-square-foot placement item may include forming, finishing and curing. A separate line for work already included under that item would duplicate cost on the owner’s schedule. Add temporary protection, cleanup and similar requirements to the cost calculation even when they have no standalone pay item. Keep notes in the estimate so you can explain where those costs went if an owner requests a breakdown.

Convert job costs into a selling price

Price the labor, materials, subcontractors, equipment and disposal that each operation requires. Ask suppliers to specify material grade, delivery and any charges for a small load or waiting time. Review trade quotes for excluded tasks or missing quantities. Confirm who furnishes items such as traffic controls, a pump or testing if the documents call for them. Make the quote validity date visible in your estimate when a supplier’s offer could expire before you can buy.

Add project costs that support more than one operation, such as field supervision, temporary facilities, mobilization and site coordination. Decide how you will recover those costs through the bid schedule. Include the business overhead and profit appropriate to the job. To apply a markup, multiply your defined cost base by one plus the markup rate. To target a margin on the selling price, divide the same cost base by one minus the target margin. Name the cost base before applying either calculation.

Tie any allowance to an uncertain scope and describe how you will reconcile it. For example, a design may show a nominal depth of base while leaving the extent of soft subgrade to be confirmed after removal. Estimate the known work using the documented dimensions and clarify how any additional excavation will be measured and approved. On a required public bid form, follow its instructions about what can be qualified and where alternatives may be submitted.

Review the bid before sending it and track changes after award

Read the final scope from the customer’s point of view. State what you will build, remove, protect and clean up. Include the schedule assumptions and any price validity limit. A fixed-price proposal needs clearly bounded work and a way to approve changes. For a unit-price proposal, state how completed quantities will be measured and when the owner will review them. Price any optional scope on a separate line so the customer can see what its approval would add.

Run a second pass on quantity extensions and schedule totals. Check that the estimate reflects the latest documents and that related items use compatible units. Compare crew and equipment days to the proposed schedule and verify that the delivery sequence is feasible. Make sure subcontractor quotes are still valid and check who covers interfaces between trades. Where the owner supplies a form, reconcile its total against your worksheet and review the requested acknowledgments and attachments.

If you win the work, brief the project lead on the scope limits and production assumptions. Track measured quantities, labor hours, equipment time and disposal tickets as you build. When site conditions or the owner’s request changes the work, identify the changed scope, price and schedule effect and obtain the agreed approval. After completion, compare the estimate with the actual job costs. Keep the measurements and production notes alongside the closeout so the next bid can use your own evidence.

Frequently asked questions

Can I use municipal bid-tab prices for my own quote?

Use them to see how contractors price measured work under a published specification. Check the city, date, quantities, payment descriptions and surrounding work. Work out your selling price from your own labor, material, equipment and site costs before quoting a private customer.

What is the difference between a lump sum and a unit price?

A lump sum is the price for a defined scope. A unit price is applied to the measured quantity of an item, such as square feet of concrete removal. Review how the bid documents define the scope, how quantities are verified and how the contract handles changes.

How do I bid when some site quantities are unknown?

Identify what can be measured, ask for clarification and follow the bid documents. If the customer permits it, specify a measurable allowance or a separate unit price for changed quantities, and say who verifies them. Record the condition in the estimate and in the handoff to the project lead.

What belongs in a small contractor’s final proposal?

Include the job location, customer, scope, drawing or specification references, measured items, total, planned schedule, and the process for approving changed work. If your price depends on owner-supplied access, utilities or materials, say who will provide them and by when.